Delays Hit Tororo-Gulu Railway Project as URC Cites Extreme Weather Challenges

By David Ochieng | Wednesday, January 29, 2025
Delays Hit Tororo-Gulu Railway Project as URC Cites Extreme Weather Challenges
President Museveni at the launch of SGR consturction in Tororo

The rehabilitation of the Tororo-Gulu railway line is facing significant delays due to unexpected design challenges and extreme weather conditions, officials from the Uganda Railways Corporation (URC) have revealed.

During a joint monitoring visit by officials from the Ministry of Works and Transport and URC in Tororo, Chief Civil Engineer Isaac Natukunda stated that progress on the project, awarded to China Roads and Bridge Corporation (CRBC) in August 2023, stands at only 23% despite 17 months of work on a 24-month timeline.

“We have had abnormal rains for the past one year that made our works very difficult, for instance, in areas like Awojja,” Natukunda explained.

Despite the setbacks, CRBC remains confident in its ability to complete the project without compromising quality.

Topics You Might Like

Delays Hit Tororo-Gulu Railway Project as URC Cites Extreme Weather Challenges News

“I remember when we just made a groundbreaking for this project, many thought we didn’t have the capacity to handle the work, but here we are,” said Dai Dexin, the Country Manager for CRBC.

Project Manager Wu Yaguang reassured stakeholders of the company’s commitment, saying, “We have every capacity needed to get this work done. Please trust us.”

The Tororo-Gulu railway rehabilitation project includes drainage improvements, earthworks, utility relocation, and railway track relaying.

Once completed, it is expected to have a transformative impact on the Bukedi, Bugisu, Teso, Lango, and Acholi sub-regions by improving connectivity to global markets and reducing transportation costs.

Benon Kajuna, Director of Transport at the Ministry of Works and Transport, emphasized the economic significance of the project.

“Once works are done, we shall have the cheapest cost in transportation of goods to the outside countries. So, this is going to be a great infrastructural development,” he stated.

While the delays present a challenge, government and project officials remain optimistic about the railway’s long-term benefits, which could significantly boost trade and economic growth in northern and eastern Uganda.

What’s your take on this story?

Join 80,000+ others on WhatsApp

Get Ahead of the News.
Stay in the know with real-time breaking news alerts, exclusive reports, and updates that matter to you.

Tap ‘Yes, Keep Me Updated’ and never miss what’s happening in Uganda and beyond—first and fast from NilePost.