Kagina explains savings to government as UNRA faces COSASE

By Amon Katungulu | Wednesday, November 9, 2022
 Kagina explains savings to government as UNRA faces COSASE
UNRA ED Allen Kagina appears before COSASE on Wednesday.

The management of the Uganda National Roads Authority(UNRA) has interfaced with  Parliament's Committee on Commissions, Statutory Authorities and State Enterprises (COSASE)  over queries highlighted in the Auditor General's report for June 2020/21 .

The committee probed over an unauthorised project reallocation of funds totaling shs124.4 billion as highlighted in the report.

Keep Reading

On Wednesday, UNRA management led by Allen Kagina explained that  after exhausting the available 10% limit as per the Finance and Management Act, UNRA  found itself in a situation where it remained with funds on slow moving projects and yet fast moving projects, like those with already acquired right of way, had exhausted their allocated funds during that period.

Kagina explained that towards end of the financial year, UNRA was going to have a huge debt which she said would have attracted interest as a result of delayed payment to contractors.

Topics You Might Like

uganda UNRA COSASE Allen Kagina Ugandan News  Kagina explains savings to government as UNRA faces COSASE News

As  a result,  she said shs124.4 billion  was reallocated after numerous engagements with the UNRA Board and the Permanent Secretary in the Ministry of Finance.

"This was therefore done to save government of Uganda and taxpayers from incurring extra cost  and burden of interest to a tune of shs22 billion  annually or shs61 million daily,"Kagina told the MPs on the committee.

The legislators however observed that this was not supported within the laws, a flaw that UNRA management  admitted but insisted it was done in the best interest of the country and saving huge sums of money for government.

In relation to employee costs, UNRA management pointed out that due to a temporary freeze on recruitment, and due to the ongoing rationalisation program, shs4.6 billion  couldn't be absorbed under employee related costs and funds were thus diverted to pay  pending invoices on road works, again to save government from further costs.

The MPs  also pointed out that this was not acceptable and that UNRA committed a sin.

They requested management to submit further accountability to ensure that the allocated monies were put to right use.

The committee  will tomorrow, Thursday continue with the interface with UNRA management over queries in the Auditor General's report.

 

What’s your take on this story?

Get breaking news first — follow us

Get Ahead of the News.
Stay in the know with real-time breaking news alerts, exclusive reports, and updates that matter to you.

Tap ‘Yes, Keep Me Updated’ and never miss what’s happening in Uganda and beyond—first and fast from NilePost.