Loadshedding frustrates Wakiso fuel terminal construction
Ugandans
hopes of affordable fuel prices will have to wait longer as persistent load
shedding affects the progress of a fuel storage terminal at Bugiri-Bukasa in
Wakiso district.
The
construction of the terminal along Entebbe road that started last year has
stalled because of unreliable power supply. President Yoweri Museveni launched
the construction of the terminal off Kawuku in June 2017.
Investor,
Ravi Shankar for Mahathi Infra Uganda Limited is frustrated by the recent load
shedding in areas of Kawuku where they are constructing the fuel store.
Unreliable
electricity supply has made the task of building the fuel store along Lake
Victoria in Kawuku very difficult. The store is to stand on 50 acres of land.
Shankar,
who is the managing director, says the heavy construction requires steady
supply of electricity but this has not been available.
To try and
keep to construction schedule, the company has been forced to hire generators.
Shankar explains, "These generators produce a lot of noise on top of
consuming too much fuel on a daily, and we work for twelve hours a day.”
This is not
the only challenge, the project has run into since it started. Shankar says,
the road from Kawuku off Entebbe road into Bugiri-Bukasa is in poor condition.
The road is narrow, full of potholes and uneven yet they need to transport
heavy machinery. They have sometimes ended up driving through residents'
compounds.
Captain
Mike Mukula, the board chair Mahathi Infra Uganda Limited, says they have been
working under many challenges to complete the project on time.
The comments
were made during a tour bya delegation from Kenya and Rwanda to first track its
progress since it benefits all countries on the northern corridor route.
Mahathi
Infra Uganda Limited (MIUL) was contracted to build the ships at Bugiri-Bukasa
and this will transport fuel from Kisumu through Lake Victoria to Bukasa and
its here that fuel will be distributed to all parts of the country. The
facility will have tanks that will store fuel.
At the
launch, Mr Museveni said water transport is the cheapest means of transport,
followed by rail transport, road and air transport. “On land, we are working on
the rail… We are also building dams to make the cost of electricity affordable,
which will attract more investors,” he added.
The
terminal is supposed to be operational June 2019.